项目治理与PMO · PMP 练习题解析

整合管理 简单 Process 过程域 题号 PMP202611-096

题目

项目管理办公室(PMO)的主要职能是以多种方式支持项目经理。以下哪项不属于这些职能?
A primary function of a project management office (PMO) is to support project managers in various ways. Which of the following is NOT one of those functions?

选项

  1. A.Intervening directly in project execution without involving the project manager
  2. B.Managing shared resources across all projects administered by the PMO
  3. C.Identifying and developing project management methodology, best practices, and standards
  4. D.Coaching, mentoring, training, and oversight
正确答案:A

解析

解析:PMO 负责共享资源管理、方法论与标准建设、辅导培训、合规审计以及跨项目沟通协调。它通常不会绕开项目经理直接接管项目执行。 Rationale:PMOs manage shared resources, develop methodology and standards, coach and train, audit compliance, and coordinate communication across projects. They do not normally take over project execution behind the project manager's back.