资源规划与获取 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-611

题目

你在估算各活动所需时间,使用一份包含人力、材料、设备类别,以及技能等级、认证要求和物资品级的文件。主要应参考哪份文件?
You are estimating how much time each activity requires, using a document that contains categories of labor, material and equipment, skill levels, required certifications and grade levels for supplies. Which document do you primarily refer to?

选项

  1. A.Resource breakdown structure
  2. B.Organizational breakdown structure
  3. C.Work breakdown structure
  4. D.Risk breakdown structure
正确答案:A

解析

解析:资源分解结构按类别与类型层级化列出团队与实物资源,细化到可与 WBS 配合进行计划与控制的程度。 Rationale:The resource breakdown structure hierarchically lists team and physical resources by category and type, down to detail usable with the WBS for planning and control.