在与客户的初步沟通中,客户要求粗略估算工期。项目经理依据三个类似项目的经验给出 8~10 个月。她用了哪种估算技术?
In initial discussions about an upcoming project, the customer asks for a rough duration estimate. Based on her experience with three similar projects, the PM provides 8-10 months. What estimation technique did she use?
选项
- A.Expert judgment
- B.Three-point estimating
- C.Analogous estimating
- D.Bottom-up estimating
解析
解析:用类似项目的历时数据给出大致量级,就是类比估算,在信息有限时最常用。
Rationale:Using historical duration data from comparable projects to produce a ballpark figure is analogous estimating, typical when detail is scarce.