整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-612

题目

检查中发现与上次完全相同的缺陷。此前修复该缺陷的变更请求已获批准,但团队从未实施。什么做法本可以防止这种情况?
During an inspection, the team detects the same defect already identified previously. A change request to repair the defect had been approved, but the team never implemented it. What could have helped prevent this?

选项

  1. A.Holding an approved change requests review
  2. B.Conducting a retrospective meeting
  3. C.Performing a root cause analysis
  4. D.Creating a quality report
正确答案:A

解析

解析:团队必须确保已批准的变更被实施、测试并确认;对已批准变更请求进行评审,正是能发现“批了没做”的控制动作。 Rationale:The team must ensure approved change requests are implemented, tested and certified; reviewing approved change requests is the control that catches unimplemented approvals.

同考点练习题