题目
检查中发现与上次完全相同的缺陷。此前修复该缺陷的变更请求已获批准,但团队从未实施。什么做法本可以防止这种情况?
During an inspection, the team detects the same defect already identified previously. A change request to repair the defect had been approved, but the team never implemented it. What could have helped prevent this?
选项
- A.Holding an approved change requests review
- B.Conducting a retrospective meeting
- C.Performing a root cause analysis
- D.Creating a quality report
解析
解析:团队必须确保已批准的变更被实施、测试并确认;对已批准变更请求进行评审,正是能发现“批了没做”的控制动作。
Rationale:The team must ensure approved change requests are implemented, tested and certified; reviewing approved change requests is the control that catches unimplemented approvals.