活动估算与估算精度 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-312

题目

项目规划期间,项目经理对某任务采用三点估算:乐观 4 天、最可能 7 天、悲观 16 天。PERT 估算是多少?
During project planning, the project manager uses a three-point estimate for a task: Optimistic = 4 days, Most Likely = 7 days, Pessimistic = 16 days. What is the PERT estimate?

选项

  1. A.7.5 days
  2. B.9 days
  3. C.9.5 days
  4. D.8 days
正确答案:D

解析

解析:D 正确。PERT 公式为(O + 4M + P)÷ 6 =(4 + 28 + 16)÷ 6 = 48 ÷ 6 = 8 天。PERT 把最可能值赋予 4 倍权重,形成反映现实不确定性的加权平均。简单平均(O+M+P)/3 = 9,但 PERT 采用 1:4:1 加权。 Rationale:D is correct. PERT formula: (O + 4M + P) ÷ 6 = (4 + 4×7 + 16) ÷ 6 = (4 + 28 + 16) ÷ 6 = 48 ÷ 6 = 8 days. The PERT estimate weights the most likely estimate four times more heavily than the optimistic or pessimistic, producing a weighted average that reflects realistic uncertainty. The simple average ((O+M+P) ÷ 3) would give 9, but PERT specifically uses the 1:4:1 weighting.