项目经理用蒙特卡洛模拟做进度风险分析:12 个月对应 70% 置信度,14 个月对应 90% 置信度。发起人要一个项目日期,项目经理应如何建议?
A project manager is using Monte Carlo simulation for schedule risk analysis. The simulation output shows a 70% confidence level at 12 months and a 90% confidence level at 14 months. The sponsor asks for the project date. What should the project manager recommend?
选项
- A.13 months: split the difference between the two confidence levels.
- B.Use 10 months: the optimistic end of the range to motivate the team.
- C.12 months: use the most likely estimate.
- D.Present the range with confidence levels to the sponsor, allowing them to decide their risk tolerance. Recommend 14 months if the organisation requires high confidence, or 12 months if they are comfortable with 30% chance of overrun.
解析
解析:D 正确。蒙特卡洛结果最有价值的呈现方式是“区间 + 置信度”,让决策者依据自身风险容忍度选择,而不是给出一个虚假的单点日期。哪种置信度合适取决于业务情境(如手术排期要求 90% 以上,内部工具升级可接受 70%)。只给单一数字(C、A、B)等于丢弃了蒙特卡洛独有的概率信息。
Rationale:D is correct. Monte Carlo output is most useful when presented as a range with confidence levels. This gives decision-makers information about their risk tolerance rather than a false single-point estimate. The sponsor's business context determines which confidence level is appropriate (a patient's surgery schedule requires 90%+; an internal tool upgrade may accept 70%). Giving a single number (C, A, B) discards the probabilistic information that Monte Carlo uniquely provides.