题目
某活动乐观估算 6 天、最可能 10 天、悲观 20 天。该活动的 PERT 标准差是多少?
A project has an activity with an optimistic estimate of 6 days, most likely of 10 days and pessimistic of 20 days. What is the PERT standard deviation for this activity?
选项
- A.2.33 days
- B.4.67 days
- C.3.5 days
- D.2.67 days
解析
解析:A 正确。PERT 标准差公式 σ =(P − O)÷ 6 =(20 − 6)÷ 6 = 14 ÷ 6 ≈ 2.33 天。标准差衡量估算的离散程度,越大表示不确定性越高。PERT 均值 =(O + 4M + P)÷ 6 =(6 + 40 + 20)÷ 6 = 66 ÷ 6 = 11 天。标准差公式中不使用最可能值。
Rationale:A is correct. PERT standard deviation formula: σ = (P − O) ÷ 6 = (20 − 6) ÷ 6 = 14 ÷ 6 = 2.33 days. The standard deviation measures the spread of the estimate: a larger standard deviation indicates greater uncertainty. The PERT mean = (O + 4M + P) ÷ 6 = (6 + 40 + 20) ÷ 6 = 66 ÷ 6 = 11 days. The standard deviation never uses the Most Likely value.