活动估算与估算精度 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-406

题目

某活动乐观估算 6 天、最可能 10 天、悲观 20 天。该活动的 PERT 标准差是多少?
A project has an activity with an optimistic estimate of 6 days, most likely of 10 days and pessimistic of 20 days. What is the PERT standard deviation for this activity?

选项

  1. A.2.33 days
  2. B.4.67 days
  3. C.3.5 days
  4. D.2.67 days
正确答案:A

解析

解析:A 正确。PERT 标准差公式 σ =(P − O)÷ 6 =(20 − 6)÷ 6 = 14 ÷ 6 ≈ 2.33 天。标准差衡量估算的离散程度,越大表示不确定性越高。PERT 均值 =(O + 4M + P)÷ 6 =(6 + 40 + 20)÷ 6 = 66 ÷ 6 = 11 天。标准差公式中不使用最可能值。 Rationale:A is correct. PERT standard deviation formula: σ = (P − O) ÷ 6 = (20 − 6) ÷ 6 = 14 ÷ 6 = 2.33 days. The standard deviation measures the spread of the estimate: a larger standard deviation indicates greater uncertainty. The PERT mean = (O + 4M + P) ÷ 6 = (6 + 40 + 20) ÷ 6 = 66 ÷ 6 = 11 days. The standard deviation never uses the Most Likely value.