活动估算与估算精度 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-049

题目

项目经理采用自下而上的估算方法。该方法的主要缺点是什么?
A project manager uses Bottom-Up estimating. What is the main disadvantage of this method?

选项

  1. A.It is highly inaccurate
  2. B.It is time-consuming and costly
  3. C.It lacks sufficient detail
  4. D.It depends heavily on external data
正确答案:B

解析

解析:自下而上估算因为逐项估算工作包而准确度高,但需要投入大量时间和精力汇总。 Rationale:Bottom-up estimation is highly accurate because it estimates work packages individually, but it requires significant time and effort to compile.