识别相关方与登记册 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-609

题目

组织设有 PMO,确保各类项目文件齐备、流程依规范执行。对于刚启动的项目,项目经理首先应查阅什么来识别相关方?
An organization's PMO ensures all relevant project documents are created and processes followed. What should the PM review first to identify stakeholders for a newly started project?

选项

  1. A.The business documents as a source of information about the project's stakeholders
  2. B.The communications management plan to learn about stakeholders
  3. C.The stakeholder engagement plan to identify engagement strategies
  4. D.The requirements documentation for information on potential stakeholders
正确答案:A

解析

解析:商业论证与效益管理计划(即商业文件)在项目前期即已形成,列出了受影响的相关方与受益者,是最早可用的信息来源。 Rationale:The business case and benefits management plan (business documents) are created pre-project and identify affected stakeholders and beneficiaries — the earliest available source.