题目
组织设有 PMO,确保各类项目文件齐备、流程依规范执行。对于刚启动的项目,项目经理首先应查阅什么来识别相关方?
An organization's PMO ensures all relevant project documents are created and processes followed. What should the PM review first to identify stakeholders for a newly started project?
选项
- A.The business documents as a source of information about the project's stakeholders
- B.The communications management plan to learn about stakeholders
- C.The stakeholder engagement plan to identify engagement strategies
- D.The requirements documentation for information on potential stakeholders
解析
解析:商业论证与效益管理计划(即商业文件)在项目前期即已形成,列出了受影响的相关方与受益者,是最早可用的信息来源。
Rationale:The business case and benefits management plan (business documents) are created pre-project and identify affected stakeholders and beneficiaries — the earliest available source.
同考点练习题
-
PMP202611-086 · 答案 D
-
PMP202611-162 · 答案 B
-
PMP202611-207 · 答案 D
-
PMP202611-547 · 答案 B