项目经理对新项目采用类比估算。最相关的类似项目耗时 8 个月、成本 40 万美元。新项目评估为复杂度高 25%。估算结果是多少?
A project manager is using analogous estimating for a new project. The most relevant similar project took 8 months and cost $400,000. The new project is assessed to be 25% more complex. What are the estimates?
选项
- A.6 months and $300,000
- B.10 months and $400,000
- C.8 months and $500,000
- D.10 months and $500,000
解析
解析:D 正确。类比估算要把复杂度系数同时施加于工期与成本:工期 8 × 1.25 = 10 个月;成本 400,000 × 1.25 = 500,000 美元。类比估算基于类似项目历史数据并按已知差异调整,速度快但精度低于参数估算或自下而上估算。在无其他区分信息时,时间与成本两个维度都应按同一复杂度系数调整。
Rationale:D is correct. Analogous estimating applies the complexity factor to both time and cost: Duration = 8 × 1.25 = 10 months. Cost = $400,000 × 1.25 = $500,000. Analogous estimating uses historical data from similar projects adjusted for known differences. It is faster and less accurate than parametric or bottom-up estimates. Both dimensions (time and cost) should be adjusted by the same complexity factor when no other information differentiates them.
同考点练习题
-
PMP202611-018 · 答案 B
-
PMP202611-049 · 答案 B
-
PMP202611-164 · 答案 C
-
PMP202611-312 · 答案 D
-
PMP202611-389 · 答案 D
-
PMP202611-406 · 答案 A
-
PMP202611-429 · 答案 C
-
PMP202611-450 · 答案 B