活动估算与估算精度 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-335

题目

项目经理对新项目采用类比估算。最相关的类似项目耗时 8 个月、成本 40 万美元。新项目评估为复杂度高 25%。估算结果是多少?
A project manager is using analogous estimating for a new project. The most relevant similar project took 8 months and cost $400,000. The new project is assessed to be 25% more complex. What are the estimates?

选项

  1. A.6 months and $300,000
  2. B.10 months and $400,000
  3. C.8 months and $500,000
  4. D.10 months and $500,000
正确答案:D

解析

解析:D 正确。类比估算要把复杂度系数同时施加于工期与成本:工期 8 × 1.25 = 10 个月;成本 400,000 × 1.25 = 500,000 美元。类比估算基于类似项目历史数据并按已知差异调整,速度快但精度低于参数估算或自下而上估算。在无其他区分信息时,时间与成本两个维度都应按同一复杂度系数调整。 Rationale:D is correct. Analogous estimating applies the complexity factor to both time and cost: Duration = 8 × 1.25 = 10 months. Cost = $400,000 × 1.25 = $500,000. Analogous estimating uses historical data from similar projects adjusted for known differences. It is faster and less accurate than parametric or bottom-up estimates. Both dimensions (time and cost) should be adjusted by the same complexity factor when no other information differentiates them.

同考点练习题