某敏捷团队被要求为一种从未做过的新类型工作估算工作量以编预算。最诚实有效的做法是什么?
An agile team is asked to estimate the effort for a completely new type of work they have never done before, to provide a budget forecast. What is the most honest and effective approach?
选项
- A.Provide a single-point estimate based on expert judgment.
- B.Use a previous project's cost as the estimate regardless of the differences.
- C.Provide a wide range estimate with explicit uncertainty disclosure, recommend a discovery spike before committing to a tighter estimate, and stage the budget forecast as confidence increases through early delivery.
- D.Refuse to estimate: unknown work cannot be estimated.
解析
解析:C 正确。对真正新颖的工作,最专业的做法是:给宽区间并明说不确定性,先安排探针降低不确定性,再逐步收紧细节——这正是“不确定性锥”的含义,估算随学习而收敛。虚构单点估算(A)制造虚假精确感;完全拒绝(D)没有帮助;直接类比无关项目(B)可能严重失真并误导。
Rationale:C is correct. For genuinely novel work, honest range estimates with explicit uncertainty, combined with a spike to reduce uncertainty before committing to detailed plans, is the most professional approach. This is the "cone of uncertainty" concept: estimates improve as learning occurs. A false single-point estimate (A) creates a false sense of precision. Refusing entirely (D) is unhelpful. Direct analogy from an unrelated project (B) may be wildly inaccurate and misleading.