活动估算与估算精度 · PMP 练习题解析

进度管理 困难 Process 过程域 题号 PMP202611-164

题目

在计划扑克中,同一用户故事的估算从 2 点到 13 点不等。接下来应该怎么做?
During planning poker, estimates for one user story range from 2 to 13 points. What should happen next?

选项

  1. A.Take the average.
  2. B.Use the estimate of the most senior developer.
  3. C.Ask the people with the highest and lowest estimates to explain their thinking, then estimate again.
  4. D.Skip the story this sprint.
正确答案:C

解析

解析:估算差异过大说明对工作的理解不一致。讨论两端意见能暴露隐藏风险或更简单的方案;取平均只会掩盖分歧。 Rationale:A wide spread shows different understanding of the work. Discussing the extremes brings out hidden risks or simpler solutions; averaging hides the disagreement.