题目
发起人要求为一个名为“客户门户”的可交付成果提供可靠的成本与时间估算。团队表示该成果规模过大,无法有把握地估算。你应该怎么做?
The sponsor asks for a reliable cost and time estimate for a deliverable called “customer portal.” The team says the deliverable is too large to estimate with confidence. What should you do?
选项
- A.Use the sponsor’s target budget as the estimate.
- B.Work with the team to decompose the portal into smaller work packages.
- C.Add 30% contingency to a rough guess.
- D.Outsource the portal so the vendor gives the estimate.
解析
解析:把范围分解为工作包可以提升估算准确性。考纲将“分解范围”列为核心使能因素。目标预算不是估算;给猜测加余量只是掩盖真实的不确定性。
Rationale:Breaking scope down into work packages makes estimates more accurate. The ECO lists “break down scope” as a core enabler. A target budget isn’t an estimate, and padding a guess hides real uncertainty.