题目
项目共识别 20 个风险,17 个转化为问题,其中多数被成功处理。收尾时项目经理更新经验教训登记册。为了让其他项目经理受益,最应写入的是什么?
20 risks were identified, 17 became issues and most were successfully managed. In closing, the PM updates the lessons learned register. Which content is most important so other PMs can benefit?
选项
- A.Lessons learned about the number of risks on a project
- B.Knowledge gained about the risk response plans and what did and did not work well
- C.Lessons learned about the resources who worked on risks
- D.Knowledge gained about how risks were identified
解析
解析:既然多数但并非全部已发生的风险处理得当,最有借鉴价值的就是哪些应对计划奏效、哪些没奏效。
Rationale:Since most but not all realized risks were managed well, the highest-value transferable knowledge is which response plans worked and which did not.
同考点练习题
-
PMP202611-015 · 答案 B
-
PMP202611-023 · 答案 B
-
PMP202611-132 · 答案 B
-
PMP202611-154 · 答案 B
-
PMP202611-181 · 答案 B
-
PMP202611-275 · 答案 A
-
PMP202611-328 · 答案 C
-
PMP202611-382 · 答案 A