质量管理计划与目的 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-598

题目

敏捷项目进行到一半时,新成员加入。他们精通预测型方法但毫无敏捷背景。随项目推进,客户满意度开始下滑。最可能的原因是:
Midway into an agile project, new members join. They are experienced with predictive approaches but have no agile background. As the project progresses, customer satisfaction starts to drop. What is the most likely reason?

选项

  1. A.The new team members did not productively contribute to the team's velocity.
  2. B.The project manager did not invite the new team members to the kick-off meeting.
  3. C.The new team members resisted changes requested by the customer.
  4. D.Customers are always unsatisfied regardless of how well the project is doing.
正确答案:C

解析

解析:预测型背景的人容易抗拒变更、死守计划,违背“响应变化高于遵循计划”和“欣然接受需求变更”,最终表现为客户满意度下降。 Rationale:Predictive-background members tend to resist change and cling to the plan, violating 'responding to change over following a plan' and 'welcome changing requirements' — which shows up as lower customer satisfaction.

同考点练习题