资源管理 困难 People 人域 题号 PMP202611-600

题目

某水电项目进度提前、低于预算,客户满意。按资源管理计划,你已用适当工具识别出团队的优势与短板。下一步应当做什么?
A hydroelectric project is ahead of schedule and under budget, and the customer is pleased. Following the resource management plan, you used appropriate tools to identify the team's strengths and weaknesses. What should you do next?

选项

  1. A.No action is required since the project is expected to exceed project objectives
  2. B.Select topics and develop the agenda for a team development meeting
  3. C.Submit a change request to modify the resource management plan
  4. D.Utilize individual and team assessment tools and techniques
正确答案:B

解析

解析:评估出优势与短板之后,建设团队的下一步是据此采取行动——会议正是讨论并解决团队发展议题的工具。 Rationale:After assessment identifies strengths and weaknesses, the next step in Develop Team is to act on them — meetings are the tool for discussing and addressing development topics.