题目
公司对一款新 App 的用户接受度没把握,于是先用敏捷方式做出只含必备功能的早期版本,若反馈良好,再用预测型方式开发完整功能版。这个早期版本代表什么?
A company considering a new mobile app is unsure how users will adopt it, so it develops an early release incrementally with only must-have features, then proceeds with the full-featured app using a predictive approach if feedback is positive. What does the early release represent?
选项
- A.Agile release planning
- B.Minimum viable product
- C.Fully functioning prototype
- D.Work breakdown structure
解析
解析:MVP 只做“能否成功部署”所必需的功能,先投放给用户检验想法,再决定是否全量投入。
Rationale:An MVP concentrates only on features absolutely necessary for successful deployment, then exposes it to users to test the idea before full investment.