质量保证与审计 · PMP 练习题解析

质量管理 中等 Process 过程域 题号 PMP202611-594

题目

某电动车发动机零件产线项目,首次试产不合格率极高。独立质量审计发现是检验规程本身有缺陷,绝大多数被质疑的零件其实符合规格。下一步应当做什么?
On an EV engine-parts production line project, the first run shows an unacceptably high failure rate. An independent quality audit reports that the inspection routine was flawed and that most questionable parts do meet specifications. What is your next step?

选项

  1. A.Meet with the production line design team to determine what changes need to be made to the line
  2. B.Update the quality management plan to remove the flawed inspection routine
  3. C.Meet with the quality team to determine what changes are required in the quality management plan
  4. D.Update the scope, schedule and cost baselines to incorporate an improved inspection routine
正确答案:C

解析

解析:审计问题出在检验规程,说明质量管理计划需要修改;先与质量团队确定改什么,再走整体变更控制。 Rationale:The audit points to the inspection routine, so the quality management plan needs changes; determine what changes with the quality team, then run them through integrated change control.