题目
某敏捷团队的发布回顾会讨论了发版前几周才爆发的破坏性风险。这些风险在发布规划早期就已识别,但关联的用户故事价值较低。怎样做才能避免风险拖到临近发版才发生?
An agile team's release retrospective discusses disruptive risk events that occurred just before release. The risks were identified early but were tied to relatively low-value user stories. What could have been done to avoid these risks occurring so close to release?
选项
- A.Overtime should have been authorized, and resources added in the weeks leading up to the release
- B.The product owner should have written the user stories more diligently so that the risk is minimized
- C.There is really nothing that could have been done because risk events always occur just before release
- D.The product owner could have scheduled the completion of high-risk user stories in the product backlog sooner rather than later in the release cycle
解析
解析:待办排序除客户价值外还应考虑风险;高风险事项早做完,才有缓冲去消化后果。
Rationale:Backlog ordering should weigh risk alongside customer value; high-risk items completed early leave buffer to absorb the consequences.