敏捷与混合实践 困难 Process 过程域 题号 PMP202611-596

题目

某敏捷团队的发布回顾会讨论了发版前几周才爆发的破坏性风险。这些风险在发布规划早期就已识别,但关联的用户故事价值较低。怎样做才能避免风险拖到临近发版才发生?
An agile team's release retrospective discusses disruptive risk events that occurred just before release. The risks were identified early but were tied to relatively low-value user stories. What could have been done to avoid these risks occurring so close to release?

选项

  1. A.Overtime should have been authorized, and resources added in the weeks leading up to the release
  2. B.The product owner should have written the user stories more diligently so that the risk is minimized
  3. C.There is really nothing that could have been done because risk events always occur just before release
  4. D.The product owner could have scheduled the completion of high-risk user stories in the product backlog sooner rather than later in the release cycle
正确答案:D

解析

解析:待办排序除客户价值外还应考虑风险;高风险事项早做完,才有缓冲去消化后果。 Rationale:Backlog ordering should weigh risk alongside customer value; high-risk items completed early leave buffer to absorb the consequences.