资源日历显示场地准备所需挖掘机存在排期冲突。你决定用当前可用的更大机型替代。下一步应当做什么?
A resource calendar shows a scheduling conflict with the excavator needed for site preparation. You decide to substitute a larger model that is currently available. What should you do next?

选项

  1. A.Update the project schedule
  2. B.Modify the project charter
  3. C.Revise the resource requirements
  4. D.Submit a change request to adjust the cost baseline
正确答案:C

解析

解析:资源需求文件记录各活动所需资源的类型与数量;换成更大机型就必须更新,以反映实际获取的资源。 Rationale:The resource requirements document records types and quantities per activity; substituting a larger excavator requires updating it to reflect the resource actually acquired.