某水处理厂项目处于规划阶段,项目经理正准备编制变更管理计划。组织设有支持型 PMO。该 PMO 可能扮演什么角色?
A PM in the planning stage of a water treatment facility project is preparing to develop the change management plan. The organization has a supportive PMO. What role might the PMO play?
选项
- A.The PMO will prepare the change management plan for the project
- B.A PMO assists with project execution and would not be involved in project planning
- C.Supply a template for the change management plan
- D.The project manager reports to the PMO, and the PMO directly manages the project
解析
解析:支持型 PMO 提供的是咨询性支持:模板、最佳实践、培训、信息渠道与经验教训,而不是直接管理项目。
Rationale:A supportive PMO provides a consultative role: templates, best practices, training, information access and lessons learned — not direct project management.