敏捷与混合实践 中等 Process 过程域 题号 PMP202611-591

题目

项目收尾会上,一位相关方提出改进供应商交付物功能的建议,却无人理会、很快被搁置。最可能的原因是什么?
During a project closure meeting, a stakeholder suggests an improvement to a vendor's deliverable. The suggestion gets no attention and is dropped. What is the most likely reason?

选项

  1. A.Suggestions are not allowed during project closure.
  2. B.The project team has already been released.
  3. C.Stakeholder influence during project closure is low.
  4. D.The deliverable still needs to be accepted.
正确答案:C

解析

解析:到了收尾,供应商交付物已完成正式验收;工作基本做完,相关方对结果的影响力降到最低。 Rationale:By closure the vendor deliverable is already formally accepted; stakeholders' ability to change outcomes is lowest at the end because most work is done.