题目
项目收尾会上,一位相关方提出改进供应商交付物功能的建议,却无人理会、很快被搁置。最可能的原因是什么?
During a project closure meeting, a stakeholder suggests an improvement to a vendor's deliverable. The suggestion gets no attention and is dropped. What is the most likely reason?
选项
- A.Suggestions are not allowed during project closure.
- B.The project team has already been released.
- C.Stakeholder influence during project closure is low.
- D.The deliverable still needs to be accepted.
解析
解析:到了收尾,供应商交付物已完成正式验收;工作基本做完,相关方对结果的影响力降到最低。
Rationale:By closure the vendor deliverable is already formally accepted; stakeholders' ability to change outcomes is lowest at the end because most work is done.
同考点练习题
-
PMP202611-233 · 答案 A
-
PMP202611-413 · 答案 A
-
PMP202611-666 · 答案 C