Scrum 事件与仪式 · PMP 练习题解析

敏捷与混合实践 中等 Process 过程域 题号 PMP202611-589

题目

你参加一场会议,项目经理、发起人、供应商及其他相关方共同总结经验教训。气氛喜庆,发起人满意,供应商询问后续合作机会。这是哪类会议?
You attend a meeting where the PM, sponsor, vendors and other stakeholders capture lessons learned. Attendees are celebratory, the sponsor is happy, and vendors ask about follow-on work. What type of meeting is this?

选项

  1. A.Team building meeting
  2. B.Project kick-off meeting
  3. C.Project retrospective
  4. D.Bidder conference
正确答案:C

解析

解析:项目回顾会在收尾期间召开,用于记录经验教训并转入经验教训库;合同刚关闭,所以供应商会问后续项目。 Rationale:A project retrospective is held during closure to record lessons learned and transfer them to the lessons learned repository; contracts just closed, hence vendor follow-on questions.