你正在为单个项目风险排优先级。团队刚完成概率与影响矩阵,你决定在排序时再考虑风险的其他特征。下一步应当做什么?
You are prioritizing individual project risks. The team has just completed a probability and impact matrix, and you decide to consider other characteristics of risk when prioritizing. What should you do next?
选项
- A.Conduct a risk probability and impact assessment
- B.Perform an assessment of other risk parameters
- C.Complete a risk data quality assessment
- D.Run a Monte Carlo simulation
解析
解析:其他风险参数评估就是考虑概率与影响之外的特征——紧迫性、临近度、关联性、潜伏性、可管理性等,用于排序。
Rationale:Assessing other risk parameters means considering characteristics beyond probability and impact — urgency, proximity, connectivity, dormancy, manageability — for prioritization.