题目
向团队解释“管理沟通”过程的工具与技术时,下列哪句表述是正确的?
Which statement would you use to correctly explain the tools and techniques of the Manage Communications process to your project team?
选项
- A.Political awareness can be useful in helping the project manager maintain stakeholder support throughout a project.
- B.An organization's culture is not a factor that influences the organization's communication technology.
- C.Once a communication method is established with the membership of the stakeholder community, it should not be changed.
- D.Presentations should consider the needs and expectations of the audience rather than the needs of the project team.
解析
解析:管理沟通依赖人际与团队技能,其中政治敏锐度帮助理解权力结构与关系网络,从而维护相关方支持。
Rationale:Managing communication relies on interpersonal and team skills, including political awareness — understanding power structures and relationships to maintain stakeholder support.