题目
某高层项目经理在获取设备时发现,资源日历显示唯一具备所需能力的塔吊存在时间冲突。项目经理希望通过小幅调整计划工作来解决。应当怎么做?
A PM acquiring equipment for a high-rise construction project finds the resource calendar shows a conflict with the only tower crane that has the required capabilities. The PM wants to address the conflict with a minor revision to the planned work. What should the PM do?
选项
- A.Adjust the project schedule to accommodate the availability of the crane
- B.Capture the information about the conflict in the lessons learned register
- C.Update the resource calendars to remove any conflicts with the crane
- D.Recommend project termination since the critical resource is unavailable
解析
解析:这本质上是进度冲突,解法是把需要塔吊的活动排到塔吊可用的时段。
Rationale:The conflict described is a scheduling conflict; it is resolved by scheduling the crane-dependent activities when the crane is available.
同考点练习题
-
PMP202611-019 · 答案 B
-
PMP202611-081 · 答案 D
-
PMP202611-089 · 答案 C
-
PMP202611-134 · 答案 B
-
PMP202611-139 · 答案 B
-
PMP202611-158 · 答案 B
-
PMP202611-188 · 答案 B
-
PMP202611-236 · 答案 B