资源规划与获取 · PMP 练习题解析

资源管理 困难 People 人域 题号 PMP202611-587

题目

某高层项目经理在获取设备时发现,资源日历显示唯一具备所需能力的塔吊存在时间冲突。项目经理希望通过小幅调整计划工作来解决。应当怎么做?
A PM acquiring equipment for a high-rise construction project finds the resource calendar shows a conflict with the only tower crane that has the required capabilities. The PM wants to address the conflict with a minor revision to the planned work. What should the PM do?

选项

  1. A.Adjust the project schedule to accommodate the availability of the crane
  2. B.Capture the information about the conflict in the lessons learned register
  3. C.Update the resource calendars to remove any conflicts with the crane
  4. D.Recommend project termination since the critical resource is unavailable
正确答案:A

解析

解析:这本质上是进度冲突,解法是把需要塔吊的活动排到塔吊可用的时段。 Rationale:The conflict described is a scheduling conflict; it is resolved by scheduling the crane-dependent activities when the crane is available.