风险识别与登记册 · PMP 练习题解析

风险管理 困难 Process 过程域 题号 PMP202611-586

题目

某 50 层住宅项目规划期间,卡车司机曾威胁罢工,会影响材料按时到场。该风险已识别并制定了应对计划。如今劳资纠纷已解决,资源可按计划供应。下一步应当做什么?
In a 50-story residential project, truck drivers had threatened to strike, which would have blocked timely material delivery. The risk was identified and a response plan developed. The dispute was settled, so resources will be available as planned. What should you do next?

选项

  1. A.Modify the resource breakdown structure
  2. B.Update the lessons learned register
  3. C.Update the issue log
  4. D.Revise the risk register
正确答案:D

解析

解析:风险登记册记录每个风险的状态;风险已被化解、未发生,就应在登记册中关闭该风险。 Rationale:The risk register records each risk's status; since the risk was averted and did not materialize, it should be closed out there.

同考点练习题