题目
某 50 层住宅项目规划期间,卡车司机曾威胁罢工,会影响材料按时到场。该风险已识别并制定了应对计划。如今劳资纠纷已解决,资源可按计划供应。下一步应当做什么?
In a 50-story residential project, truck drivers had threatened to strike, which would have blocked timely material delivery. The risk was identified and a response plan developed. The dispute was settled, so resources will be available as planned. What should you do next?
选项
- A.Modify the resource breakdown structure
- B.Update the lessons learned register
- C.Update the issue log
- D.Revise the risk register
解析
解析:风险登记册记录每个风险的状态;风险已被化解、未发生,就应在登记册中关闭该风险。
Rationale:The risk register records each risk's status; since the risk was averted and did not materialize, it should be closed out there.