知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-585

题目

某新产品开发项目提前完工且低于预算。收尾伊始,项目经理希望找出成功背后的因素以便复制。最佳做法是:
A new product development project finished ahead of schedule and under budget. Starting closure, the PM wants to identify the factors behind the success so results can be replicated. What is the best course of action?

选项

  1. A.Perform a regression analysis
  2. B.Review the risk register
  3. C.Measure stakeholder satisfaction
  4. D.Study the project's final report
正确答案:A

解析

解析:成功通常是多因素叠加的结果。回归分析通过检视多个输入变量与结果的关系,揭示哪些变量真正贡献了绩效。 Rationale:Success usually results from a combination of factors. Regression analysis examines input variables against outputs to reveal which variables contributed to the outcome.