题目
资源需求文件要求悬挂部件喷漆。针对问题日志中的一项问题,有人建议改用粉末喷涂以获得更好的耐腐蚀性。项目经理首先应当做什么?
The resource requirements documentation calls for suspension parts to be painted. In response to an issue in the issue log, powder coating is recommended for better corrosion resistance. What should the PM do first?
选项
- A.Deny the recommendation as it represents gold plating
- B.Follow the original resource requirements
- C.Purchase the powder coating equipment and supplies
- D.Submit a change request
解析
解析:把建议作为纠正措施意味着改变需求并可能增加成本,必须经批准的变更请求更新成本基准等计划内容。
Rationale:Accepting the recommendation as corrective action changes requirements and may add cost, so an approved change request is needed to update plans such as the cost baseline.