某基础设施项目经理正开始为风险排定优先级以便进一步分析。一位相关方担心现有风险信息不够准确可靠。最佳做法是:
A project manager leading an infrastructure project is starting to prioritize individual risks for further analysis. A stakeholder worries that existing risk information may not be accurate and reliable. What is the best course of action?
选项
- A.Perform the Identify Risks process again
- B.Capture the concern in the stakeholder register
- C.Perform a risk data quality assessment
- D.Conduct a risk probability and impact assessment
解析
解析:风险数据质量评估专门衡量风险数据的准确性与可靠性;数据质量不达标时,需要重新收集更可靠的数据。
Rationale:Risk data quality assessment evaluates how accurate and reliable the risk data is as a basis for qualitative analysis; low-quality data may require gathering better data.