整合管理 简单 Process 过程域 题号 PMP202611-565

题目

因燃油价格上涨,某车企启动提升燃油效率的项目以提高市场份额与盈利。下列哪项不属于项目启动的四大类根本因素?
In light of rising fuel costs, a car manufacturer initiates a project to increase fuel efficiency, aiming to improve market share and profitability. Which of the following is NOT one of the four fundamental categories of factors that lead to project initiation?

选项

  1. A.Meet regulatory or legal requirements
  2. B.Create, improve, or fix products, processes, or services
  3. C.Satisfy stakeholder requests or needs
  4. D.Implement or change business or technological strategies
正确答案:A

解析

解析:题干说的是响应市场需求,并非法规要求。因此“满足监管、法律或社会要求”这一类在此情形中并不成立。 Rationale:The scenario says the project responds to market demand, not legal requirements. Meeting regulatory/legal/social requirements is the category not represented here.