题目
你在开发一款改编自即将上映电影的电子游戏。销售总监问试玩版能否赶在电影首映前完成,你不记得确切日期。应当到哪里查?
You lead a project to develop a video game based on an upcoming movie. The sales director asks whether the demo will be ready by the movie premiere date. You don't remember the exact date. Where should you look?
选项
- A.Ask the project sponsor for the information
- B.Review the project work breakdown structure
- C.Consult the resource requirements document
- D.Check the project milestone list
解析
解析:里程碑清单记录各里程碑的计划日期,是查首映、试玩版与正式版等关键日期的首选。
Rationale:The milestone list records scheduled dates for specific milestones — the best place for key dates such as the premiere and demo/full release.