题目
供应商交付的系统未达到规格,你的上级已指示采购部门扣款,供应商则提出了未付款索赔。你首先应当做什么?
A system delivered by a vendor does not perform as specified. Your boss instructed procurement to withhold payment. The vendor has filed a claim for non-payment. What should you do first?
选项
- A.Attempt to negotiate a resolution with the vendor
- B.Do nothing as the system is not fit for use
- C.Resort to alternative dispute resolution (ADR)
- D.Contact the legal department to file suit for damages
解析
解析:无论合同条款如何,协商永远是第一步;协商不成再走 ADR,诉讼是最后手段。
Rationale:Regardless of contract terms, negotiation is always the first step; ADR follows failed negotiation, and litigation is the last resort.