每日站会上,一名程序员说她有空余时间,就加了原设计中没有的功能,认为客户会喜欢。你最佳的做法是:
During a daily stand-up, a programmer mentions she had extra time and added functionality not included in the original design, believing the customer will appreciate it. What is your best course of action?
选项
- A.Remove the added functionality and ensure that the project team builds the software as designed going forward
- B.Thank the programmer for the extra effort and notify the customer of the new functionality that has been added
- C.Update the cost baseline since the project will run over budget due to the cost of adding new functionality
- D.Accept the added functionality, but ask the programmer to build only what has been designed going forward
解析
解析:计划外的功能属于镀金,会抬高风险:可能与现有功能冲突,或客户系统根本不支持。若确有价值,应先向客户建议,再走整体变更控制提交变更请求。
Rationale:Unplanned functionality is gold plating and raises risk: it may conflict with other features or unsupported client systems. If valuable, propose it to the customer and process a change request through integrated change control.