验证范围与正式验收 · PMP 练习题解析

范围管理 困难 Process 过程域 题号 PMP202611-558

题目

每日站会上,一名程序员说她有空余时间,就加了原设计中没有的功能,认为客户会喜欢。你最佳的做法是:
During a daily stand-up, a programmer mentions she had extra time and added functionality not included in the original design, believing the customer will appreciate it. What is your best course of action?

选项

  1. A.Remove the added functionality and ensure that the project team builds the software as designed going forward
  2. B.Thank the programmer for the extra effort and notify the customer of the new functionality that has been added
  3. C.Update the cost baseline since the project will run over budget due to the cost of adding new functionality
  4. D.Accept the added functionality, but ask the programmer to build only what has been designed going forward
正确答案:A

解析

解析:计划外的功能属于镀金,会抬高风险:可能与现有功能冲突,或客户系统根本不支持。若确有价值,应先向客户建议,再走整体变更控制提交变更请求。 Rationale:Unplanned functionality is gold plating and raises risk: it may conflict with other features or unsupported client systems. If valuable, propose it to the customer and process a change request through integrated change control.

同考点练习题