方法论裁剪 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-556

题目

某风电场建在毫无通信基础设施的区域,计划用项目管理软件监控进展,并向总部每日通报状态;两支队伍轮换驻场各七天。控制进度时最可能遇到什么挑战?
A wind farm is being built in an area with no communication infrastructure; progress will be monitored with project management software and daily status updates sent to the home office. Two teams will live onsite in rotating seven-day tours. Which is the most likely challenge while controlling the schedule?

选项

  1. A.Stability of requirements
  2. B.Technology support
  3. C.Human resource availability
  4. D.Project importance
正确答案:B

解析

解析:裁剪时需要考虑技术支持条件。现场没有蜂窝网络与 Wi-Fi,要每日更新并提交进度,就得配卫星设备,并重新考虑状态通报的内容与频率。 Rationale:Tailoring considerations include technology support. With no cellular or Wi-Fi coverage, updating and submitting the schedule daily requires satellite equipment and reconsidering update content and frequency.