整合管理 中等 Process 过程域 题号 PMP202611-555

题目

某设计项目结束时,竞争对手的新技术让交付物直接过时。发起人认可团队按时按预算完成,但认为项目本该更早终止。项目经理本可以怎样做?
At the end of a design project, a competitor gained market share with a new technology that rendered the deliverable obsolete. The sponsor is pleased the team finished on time and on budget but thinks the project should have been terminated much sooner. What might the manager have done differently?

选项

  1. A.Used phases and phase gates
  2. B.Established a change control board (CCB) to review and render decisions for all submitted change requests
  3. C.Terminated the project when the new technology was introduced
  4. D.Scheduled more frequent lessons learned meetings with the project team
正确答案:A

解析

解析:阶段关口提供周期性的结构化审查,检视商业论证是否仍然成立。只有带关口的阶段化推进,才能及早发现论证失效并及时终止。 Rationale:Phase gates provide periodic structured reviews of whether the business case is still valid. Only a phased approach with gates would have surfaced the invalidation early enough to terminate.