技术员检测设备后发现缺陷,并提交了修复该缺陷的变更请求,说明修复需要大量返工。项目经理首先应当做什么?
A technician has tested a piece of equipment and found a defect, and submitted a change request to repair it, noting the repair will require significant rework. What should the project manager do first?
选项
- A.Approve the change request
- B.Consult the change management plan
- C.Instruct the team to repair the defect
- D.Reject the change request due to significant rework
解析
解析:变更管理计划规定了谁有权评审与决策变更请求。项目经理未必拥有批准权限,先查计划确认权限归属才正确。
Rationale:The change management plan defines who has authority to review and decide on change requests. The PM may lack approval authority, so checking the plan first is correct.