整体变更控制 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-554

题目

技术员检测设备后发现缺陷,并提交了修复该缺陷的变更请求,说明修复需要大量返工。项目经理首先应当做什么?
A technician has tested a piece of equipment and found a defect, and submitted a change request to repair it, noting the repair will require significant rework. What should the project manager do first?

选项

  1. A.Approve the change request
  2. B.Consult the change management plan
  3. C.Instruct the team to repair the defect
  4. D.Reject the change request due to significant rework
正确答案:B

解析

解析:变更管理计划规定了谁有权评审与决策变更请求。项目经理未必拥有批准权限,先查计划确认权限归属才正确。 Rationale:The change management plan defines who has authority to review and decide on change requests. The PM may lack approval authority, so checking the plan first is correct.

同考点练习题