经验教训与知识管理 · PMP 练习题解析

知识管理与经验 中等 Business Environment 商业环境域 题号 PMP202611-548

题目

发起人在启动阶段与团队讨论后,希望对风险做整体性梳理。公司过去做过很多规模与范围类似的项目。团队到哪儿找过往项目风险信息最合适?
A project sponsor is working with the team during project initiation. After reviewing high-level product requirements, the sponsor decides they need to look for risks from a holistic standpoint. The company has developed many similar projects in the past. Where best can the team find information about past project risks?

选项

  1. A.In previous DfX risk logs
  2. B.In previous risk breakdown structures
  3. C.In previous cause-and-effect diagrams
  4. D.In previous organizational risk thresholds
正确答案:B

解析

解析:过往风险管理计划属于组织过程资产,其中的风险分解结构可复用,帮助对当前项目的风险进行分类归集。 Rationale:Organizational process assets such as past risk management plans contain risk breakdown structures; reusing an RBS from a similar project helps categorize and classify risks for the current one.