题目
发起人在启动阶段与团队讨论后,希望对风险做整体性梳理。公司过去做过很多规模与范围类似的项目。团队到哪儿找过往项目风险信息最合适?
A project sponsor is working with the team during project initiation. After reviewing high-level product requirements, the sponsor decides they need to look for risks from a holistic standpoint. The company has developed many similar projects in the past. Where best can the team find information about past project risks?
选项
- A.In previous DfX risk logs
- B.In previous risk breakdown structures
- C.In previous cause-and-effect diagrams
- D.In previous organizational risk thresholds
解析
解析:过往风险管理计划属于组织过程资产,其中的风险分解结构可复用,帮助对当前项目的风险进行分类归集。
Rationale:Organizational process assets such as past risk management plans contain risk breakdown structures; reusing an RBS from a similar project helps categorize and classify risks for the current one.