范围管理 中等 Process 过程域 题号 PMP202611-549

题目

设计阶段外部专家已确认起重机图纸符合要求。建造阶段客户现场走访时发现部分焊缝有缺陷,必须返工。这一情况本可以如何避免?
In the design phase, external experts verified that the team's blueprints for a new crane complied with requirements. During the build phase, the customer performed a walkthrough and found that some welding joints were defective, requiring rework. How could this situation have been avoided?

选项

  1. A.Outsourcing the welding to an external vendor
  2. B.Testing the welding before the customer walkthrough
  3. C.Using the requirements traceability matrix
  4. D.Defects are part of any project and cannot be avoided.
正确答案:B

解析

解析:质量控制应在范围确认之前确保成果完整、正确并满足期望。若认真执行质量控制,焊缝缺陷会在内部就被发现并修正,而不至于在客户走访时暴露。 Rationale:Control Quality ensures outputs are complete, correct and meet expectations before Validate Scope. Proper quality control would have caught the defective welds internally rather than at the customer walkthrough.