识别相关方与登记册 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-547

题目

你刚接手一个部分交付物由外部供应商生产的项目,想了解卖方一侧的参与者。应到哪里查这些信息?
You have just taken over a project in which some of the deliverables will be produced by external vendors. You want to familiarize yourself with those who are involved in the project from the sellers' side. Where would you look to obtain this information?

选项

  1. A.Bid documents
  2. B.Stakeholder register
  3. C.Seller proposals
  4. D.Stakeholder engagement plan
正确答案:B

解析

解析:相关方登记册记录各方利益、参与程度、相互依赖、影响力与影响。供应商也是项目相关方,无论内外都应登记在其中。 Rationale:The stakeholder register records stakeholder interests, involvement, interdependencies, influence and impact. Vendors are project stakeholders and belong in it, whether internal or external.