案例背景同上。网络安全供应商迟迟未完成开发文档,系统集成存在不确定性。最佳做法是:
Case study: the cybersecurity vendor has not completed development documentation, creating uncertainty about system integration. What is the best course of action?
选项
- A.Work with the development team to draft the missing interface documentation based on prior vendor deliverables.
- B.Add additional schedule contingency to account for potential integration delays while continuing to monitor the vendor's progress.
- C.Collaborate with the vendor and development team to clarify requirements and reassess the integration approach.
- D.Ask the development team to proceed with integration assumptions based on prior experience.
解析
解析:外部依赖出问题,多半是因为期望从未说清。联合工作会面比公文往来更快暴露错位;加储备或替对方写假设性接口规范,只是接受模糊而不是消除模糊,建立在假设上的集总会在测试阶段暴露。
Rationale:External dependencies usually fail because expectations were never made explicit. A joint working session surfaces misalignment faster than formal correspondence; padding the schedule or drafting assumed specs accepts the ambiguity instead of removing it.