外部环境变化与影响评估 · PMP 练习题解析

商业环境与战略 中等 Business Environment 商业环境域 题号 PMP202611-202

题目

政府对项目所需设备加征进口关税,成本将上升 12%。你应该怎么做?
The government raises import duties on equipment your project needs. Costs will go up by 12%. What should you do?

选项

  1. A.Absorb the cost silently.
  2. B.Analyse the impact on the budget and business case, inform the sponsor and follow change control.
  3. C.Buy cheaper equipment without approval.
  4. D.Stop the project.
正确答案:B

解析

解析:外部变化会影响商业论证。分析影响并正式提出,才能让有权者决策;隐瞒变化只会在后面酿成更大问题。 Rationale:External changes can affect the business case. Analysing the impact and raising it formally lets the right people decide; hidden changes create bigger problems later.