题目
案例(续):市政府发布了限制夜间施工噪声的新规定,而你的计划依赖夜班施工。你应该如何处理这一新规定?
Case (continued): The city published a new rule limiting noise from night work, and your plan relies on night shifts. How should you handle the new rule?
选项
- A.Continue night shifts until an inspector complains.
- B.Confirm how the rule applies with compliance stakeholders and assess its impact on scope and schedule.
- C.Move all work to day shifts today without further review.
- D.Ask the team to vote on whether to follow the rule.
解析
解析:出现新的法律法规时,必须核实其要求并判断其影响程度:确认要求、评估影响,再通过变更控制更新计划。无视规定会带来法律风险。
Rationale:When a new law or rule appears, you must check it and decide how much it matters. Confirm the requirement, measure the impact, and update the plan through change control. Ignoring the rule creates legal risk.