监控项目工作与绩效 · PMP 练习题解析

整合管理 困难 Process 过程域 题号 PMP202611-545

题目

案例背景同上。团队速率持续下滑,成员反馈是行政事务与低效会议消耗了产能。项目经理应当怎么做?
Case study: velocity has steadily declined, and the team reports that administrative work and inefficient meetings are reducing productivity. What should the project manager do?

选项

  1. A.Leave reporting practices unchanged and allow the team to adjust as they gain experience.
  2. B.Add performance targets for each iteration so the team is accountable for recovering lost productivity and meeting delivery commitments.
  3. C.Ask functional managers to assign additional personnel during the remaining iterations.
  4. D.Work with the team to eliminate waste, improve workflows, and continuously refine how work is performed.
正确答案:D

解析

解析:速率衡量的是团队所处的系统,而不是个人努力。当重复报告与优先级冲突并存时,瓶颈在流程上,最贴近流程的人最能找出该简化、合并或删掉什么。加指标是把系统问题当成动机问题,加人则先增加协调成本。 Rationale:Velocity measures the system the team works in, not individual effort. When it declines amid duplicated reporting and conflicting priorities, the constraint sits in the process; the people closest to it are best placed to simplify it.