题目
案例背景同上。团队速率持续下滑,成员反馈是行政事务与低效会议消耗了产能。项目经理应当怎么做?
Case study: velocity has steadily declined, and the team reports that administrative work and inefficient meetings are reducing productivity. What should the project manager do?
选项
- A.Leave reporting practices unchanged and allow the team to adjust as they gain experience.
- B.Add performance targets for each iteration so the team is accountable for recovering lost productivity and meeting delivery commitments.
- C.Ask functional managers to assign additional personnel during the remaining iterations.
- D.Work with the team to eliminate waste, improve workflows, and continuously refine how work is performed.
解析
解析:速率衡量的是团队所处的系统,而不是个人努力。当重复报告与优先级冲突并存时,瓶颈在流程上,最贴近流程的人最能找出该简化、合并或删掉什么。加指标是把系统问题当成动机问题,加人则先增加协调成本。
Rationale:Velocity measures the system the team works in, not individual effort. When it declines amid duplicated reporting and conflicting priorities, the constraint sits in the process; the people closest to it are best placed to simplify it.
同考点练习题
-
PMP202611-111 · 答案 A
-
PMP202611-395 · 答案 D
-
PMP202611-460 · 答案 A
-
PMP202611-574 · 答案 B
-
PMP202611-608 · 答案 A
-
PMP202611-614 · 答案 B