外部环境变化与影响评估 · PMP 练习题解析

商业环境与战略 简单 Business Environment 商业环境域 题号 PMP202611-091

题目

事业环境因素指围绕或影响项目成功的内部与外部条件。以下关于这些因素的说法都成立,除了:
Enterprise environmental factors refer to internal and external conditions that surround or influence the success of a project. All of the following apply to these factors EXCEPT:

选项

  1. A.They include organizational culture, structure, and processes
  2. B.They include government or industry standards such as regulatory requirements, codes of conduct, product standards, and quality standards
  3. C.They include information technology software such as scheduling tools, configuration management systems, and information distribution systems
  4. D.They exclude personnel administration functions such as staffing and retention guidelines, performance reviews, and time tracking, because these belong to the human resources department
正确答案:D

解析

解析:人员管理政策与程序本身就是典型的事业环境因素,会制约项目获取与管理人力资源的方式。其余三项都正确描述了常见的事业环境因素。 Rationale:Personnel administration policies and procedures are explicitly listed as enterprise environmental factors because they constrain how the project acquires and manages people. The other three statements correctly describe typical EEFs.