外部环境变化与影响评估 · PMP 练习题解析

商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-131

题目

某跨国项目受到所在两国贸易法规突然变化的影响:项目关键部件的进口关税上涨 40%,对项目预算造成显著冲击。项目经理首先应该做什么?
A multinational project is affected by a sudden change in trade regulations between two countries where the project operates. Import tariffs on critical project components have increased by 40%, significantly impacting the project budget. What should the project manager do first?

选项

  1. A.Switch to domestic suppliers immediately to avoid the tariff increase
  2. B.Assess the impact on project cost, schedule, and risk, then present options to the sponsor and governance board
  3. C.Absorb the cost increase from the project's management reserve without informing stakeholders
  4. D.Request the procurement team to renegotiate all existing vendor contracts
正确答案:B

解析

解析:外部营商环境变化需要先做结构化影响评估再行动。项目经理分析其对成本、进度、风险与范围的影响,再向决策者呈报有依据的选项。未加分析就行动(更换供应商或自行吸收成本)可能带来新风险或错失更优方案。 Rationale:External business environment changes require a structured impact assessment before action. The PM analyzes effects on cost, schedule, risk, and scope, then presents informed options to decision-makers. Acting without analysis—switching suppliers or absorbing costs—may create new risks or miss better alternatives.