题目
某跨国项目受到所在两国贸易法规突然变化的影响:项目关键部件的进口关税上涨 40%,对项目预算造成显著冲击。项目经理首先应该做什么?
A multinational project is affected by a sudden change in trade regulations between two countries where the project operates. Import tariffs on critical project components have increased by 40%, significantly impacting the project budget. What should the project manager do first?
选项
- A.Switch to domestic suppliers immediately to avoid the tariff increase
- B.Assess the impact on project cost, schedule, and risk, then present options to the sponsor and governance board
- C.Absorb the cost increase from the project's management reserve without informing stakeholders
- D.Request the procurement team to renegotiate all existing vendor contracts
解析
解析:外部营商环境变化需要先做结构化影响评估再行动。项目经理分析其对成本、进度、风险与范围的影响,再向决策者呈报有依据的选项。未加分析就行动(更换供应商或自行吸收成本)可能带来新风险或错失更优方案。
Rationale:External business environment changes require a structured impact assessment before action. The PM analyzes effects on cost, schedule, risk, and scope, then presents informed options to decision-makers. Acting without analysis—switching suppliers or absorbing costs—may create new risks or miss better alternatives.
同考点练习题
-
PMP202611-010 · 答案 B
-
PMP202611-069 · 答案 B
-
PMP202611-079 · 答案 D
-
PMP202611-091 · 答案 D
-
PMP202611-115 · 答案 D
-
PMP202611-141 · 答案 B
-
PMP202611-202 · 答案 B
-
PMP202611-505 · 答案 D