案例背景同上。临床代表认为自己对项目决策了解不够。项目经理应当怎么做?
Case study: clinical representatives believe they are not receiving sufficient information about project decisions. What should the project manager do?
选项
- A.Increase the frequency of project status reports and distribute additional updates to stakeholder groups.
- B.Hold recurring meetings with clinical representatives to review project decisions and gather feedback.
- C.Update the stakeholder engagement and communications approaches.
- D.Request that the sponsor communicate major decisions to clinical stakeholders going forward.
解析
解析:问题不在通报量不够,而在参与层级不对——他们是在实施后才“被告知”。应更新相关方参与与沟通方法,重新识别相关方、评估其影响与利益、明确需要什么信息、以何种形式、在决策周期的哪个节点提供。
Rationale:The issue is ineffective engagement, not lack of messages: they learn of decisions after implementation. Updating the engagement and communications approaches addresses stakeholder level, format and timing.