题目
你负责一个公共公园建设项目,当地社区团体抗议项目选址。你在与他们会谈时履行的是哪项商业环境任务?
You are managing a project to build a public park, and a local community group protests the project's location. What business environment tasks are you performing when meeting them?
选项
- A.Managing project communications
- B.Delivering project benefits
- C.Supporting organizational change
- D.Evaluating the project's impact on the external community
解析
解析:项目经理必须考虑项目对外部环境与社会的影响。
Rationale:Project managers must consider the external environmental and social impact of projects.