外部环境变化与影响评估 · PMP 练习题解析

商业环境与战略 简单 Business Environment 商业环境域 题号 PMP202611-115

题目

项目复杂性源于多种组织行为。复杂性的维度包括以下各项,除了:
Complexity in projects arises from many organizational behaviors. The dimensions of complexity include all of the following EXCEPT:

选项

  1. A.System behavior
  2. B.Human behavior
  3. C.Ambiguity
  4. D.Process behavior
正确答案:D

解析

解析:复杂性的三个维度是系统行为(组件间相互依赖)、人的行为(人与群体互动)与模糊性(不确定与理解不足)。“过程行为”不属于其中之一。 Rationale:The three dimensions of complexity are system behavior (interdependencies), human behavior (interplay among people and groups), and ambiguity (uncertainty and lack of understanding). 'Process behavior' is not one.