题目
在另一个国家执行项目期间,政府提高了项目所需硬件的进口关税。这属于哪类变化?
During a project in another country, the government increases import taxes on hardware needed for the project. What type of change is this?
选项
- A.Internal business environment change
- B.External business environment change
- C.Poor risk planning
- D.Scope creep
解析
解析:政治与经济变化属于外部环境因素,会影响项目结果。
Rationale:Political and economic changes are part of external environmental factors that may affect project outcomes.